Designer: Payette and Associates
General Contractor: Barr & Barr, Inc.
Description: On 8/7/08, Governor Patrick signed a $ 2.2 billion higher education bond bill into law which includes $ 98.7 million for the addition/renovation of the Conant Science Building. This project will include a 171,000 square-foot addition, renovation of 43,000 square-feet and demolition of one existing wing of the building. The program will accommodate lab, teaching, research, and instruction space for Biological Sciences, Chemical Sciences, Computer Sciences, Earth Sciences, Geography, Math, and Physics. The goal for this project is to meet L.E.E.D. Silver Certification.Status: The Feasibility Study is complete, and the Design Phase is currently underway. Construction started in June 2009. On 10/30/09, the College hosted the official groundbreaking ceremony. This project will be constructed in phases. A new 171,000 square-foot addition is scheduled to be completed in July 2011. The demolition and renovation to a portion of the existing building will begin in June 2011 and will be completed in July 2012. All phases will be completed in August 2012.
Designer: Sgarzi Associates, Inc.
General Contractor: Massey Construction Corp.
Description: In the summer of 2008, the Burnell School was reverted back to the College for College programming. This former lab school for the College's School of Education & Allied Studies is undergoing phased improvements to accommodate college programs.Status: The Feasibility Study for the renovation of the entire building has been completed. Initial temporary renovation to six (6) general-purpose classrooms was completed in the summer of 2008. In the spring of 2009, a new Speech-Language-Hearing Center for the Special Education Department was completed. In the summer of 2009, interior renovation to provide five (5) additional general-purpose classrooms, as well as, improvements to the Children's Center.

Designer: Pfeufer/Richardson P.C. Architects
General Contractor: Consigli Construction Co.
Description: Complete renovation of Buildings A, B, C, & D.Status: This renovation will be done in three phases. Phase I (Buildings C&D) construction is anticipated to begin May 2009 and complete December 2009; Phase II (Building A) construction is anticipated to begin January 2010 and complete May 2010; and Phase III (Building B) construction is anticipated to begin in May 2010 and complete August 2010.
Designer: Habeeb & Associates Architects, Inc.
General Contractor: TBD
Description: Phase I will consist of a 3,200 square-foot addition which will be utilized by the Art programs; including, 2D, 3D Design Space, as well as, additional program support areas. Some of the Architectural features of the building include a new exterior handicap ramp and retaining wall, brick courtyard, translucent wall panels, and building canopies at the entrances.Status: The design phase of this project is currently underway. Funding for construction is pending.
Designer: TBD
General Contractor: TBD
Description: As part of the statewide master planning process for Massachusetts Higher Education, a new academic building is identified as a priority for the BSC campus.Status: N/A
Designer: TBD
General Contractor: TBD
Description: As part of the statewide master planning process for Massachusetts Higher Education, a new academic building is identified as a priority for the BSC campus.Status: N/A
Designer: TBD
General Contractor: TBD
Description: As part of the Crimson Hall site planning, a second new 400-bed residence hall would be sited adjacent to Crimson Hall.Status: N/A
Rondileau Campus Center - Existing |
Rondileau Campus Center - Proposed |

Rondileau Campus Center Auditorium - Existing |
Rondileau Campus Center Auditorium - Proposed |

Designer: Prellwitz/Chilinski Associates, Inc. and Connor Architecture
General Contractor: TBD
Description:Status: At this time, the feasibility study is being finalized to incorporate Mass L.E.E.D. Plus requirements. Design and construction will proceed in phases. Plans are underway to renovate the cafeteria during the summer of 2008.


Designer: Stantec (a.k.a. - Geller DeVellis, Inc.) and Sgarzi & Associates
General Contractor: TBD
Description:Status: The master plan has been completed and planning is underway to implement phased improvements.
This page is maintained by the Facilities Management and Planning Office.
Send comments and suggestions to srego@bridgew.edu.
Last Modified: November 6, 2009