Designer: Payette and Associates
General Contractor: Barr & Barr, Inc.
Description: On 8/7/08, Governor Patrick signed a $ 2.2 billion higher education bond bill into law which includes $ 98.7 million for the addition/renovation of the Conant Science Building. This project will include a 171,000 square-foot addition, renovation of 43,000 square-feet and demolition of one existing wing of the building. The program will accommodate lab, teaching, research, and instruction space for Biological Sciences, Chemical Sciences, Computer Sciences, Earth Sciences, Geography, Math, and Physics. The goal for this project is to meet L.E.E.D. Silver Certification.Status: Construction started in June 2009. On 10/30/09, the College hosted the official groundbreaking ceremony. This project will be constructed in phases. Phase One - A new 171,000 square-foot addition was completed in August 2011. The demolition and renovation to a portion of the existing building will begin in September 2011 and will be completed in July 2012. All phases will be completed in August 2012.
Click here to view Look Ahead Schedule
Click here to view additional renderings
Click here to watch Conant Science & Math Building construction on BearCAM
Designer: TBD
General Contractor: TBD
Description: As part of the statewide master planning process for Massachusetts Higher Education, a new academic building is identified as a priority for the BSU campus.Status: N/A
Designer: TBD
General Contractor: TBD
Description: As part of the statewide master planning process for Massachusetts Higher Education, a new academic building is identified as a priority for the BSU campus.Status: N/A

Designer: Walker Parking Consultants
General Contractor: Barr & Barr, Inc.
Description: New parking garage to provide parking for 840 vehicles and will be located in the Lower Great Hill parking area adjacent to the Rosen Tennis Courts. Scope will include an enclosed elevator/stair tower, entrance from Great Hill Drive, security camera system, and a standpipe system for fire protection. The structure will be constructed using a brick-clad precast concrete system.Status: Construction on this project began in May 2011 and is expected to be complete by January 2012.
Designer: Perkins + Will
General Contractor: TBD
Description: As part of the Crimson Hall site planning, a second new 500-bed residence hall will be sited adjacent to Crimson Hall.Status: This project is currently in the design/preconstruction phase. Construction is expected to begin in March 2012.
Rondileau Campus Center - Existing |
Rondileau Campus Center - Proposed |

Rondileau Campus Center Auditorium - Existing |
Rondileau Campus Center Auditorium - Proposed |

Designer: Prellwitz/Chilinski Associates, Inc. and Connor Architecture
General Contractor: TBD
Description:Status: At this time, the feasibility study is being finalized to incorporate Mass L.E.E.D. Plus requirements. Design and construction will proceed in phases. Plans are underway to renovate the cafeteria during the summer of 2008.
This page is maintained by the Facilities Management and Planning Office.
Send comments and suggestions to srego@bridgew.edu.
Last Modified: November 10, 2011